Prosecutions
Asbestos is the biggest single cause of work-related deaths in the UK, with an estimated 4,000 people dying every year.
The sentencing hearing, at Bournemouth Crown Court, resulted in the retailer being fined £1 million and ordered to pay costs of £600,000, contractor 1 being fined £200, and contractor 2 being fined £100,000 and ordered to pay costs of £40,000, all for breaches that took place at the retailers store in Reading.
Contractor 3 was fined £50,000 and ordered to pay costs of £75,000, for breaches that took place at the store in Bournemouth. Contractor 3 is applying for permission to appeal against conviction.
As a result of a prosecution brought by the Health and Safety Executive (HSE), the retailer and contractors 1 and 3 were found guilty in July 2011. Contractor 2 pleaded guilty at an earlier hearing in January 2010. The work was carried out between 2006 and 2007 on shops in Reading and Bournemouth.
During the three month trial which ended in July 2011, Winchester Crown Court heard construction workers at the two stores removed asbestos-containing materials that were present in the ceiling tiles and elsewhere.
The court heard that the client did not allocate sufficient time and space for the removal of asbestos-containing materials at the Reading store. The contractors had to work overnight in enclosures on the shop floor, with the aim of completing small areas of asbestos removal before the shop opened to the public each day.
HSE alleged that the retail company failed to ensure that work at the Reading store complied with the appropriate minimum standards set out in legislation and approved codes of practice. The company had produced its own guidance on how asbestos should be removed inside its stores, and the court heard that this guidance was followed by contractors inappropriately during major refurbishment.
Contractor 1 failed to reduce to a minimum the spread of asbestos to the Reading shop floor. Witnesses said that areas cleaned by the company were re-contaminated by air moving through the void between the ceiling tiles and the floor above, and by poor standards of work.
Contractor 2 the principal contractor at the Reading store, admitted that it should not have permitted a method of asbestos removal which did not allow for adequate sealing of the ceiling void, which resulted in risks to contractors on site.
The principal contractor at the Bournemouth store, contractor 3, failed to plan, manage and monitor removal of asbestos-containing materials. It did not prevent the possibility of asbestos being disturbed by its workers in areas that had not been surveyed extensively.
After the sentencing, the HSE's Southern Head of Operations for Construction, said:
"This outcome should act as a wake up call that any refurbishment programmes involving asbestos-containing materials must be properly resourced, both in terms of time and money - no matter what.
"Large retailers and other organisations who carry out major refurbishment works must give contractors enough time and space within the store to carry out the works safely. Where this is not done, and construction workers and the public are put at risk, HSE will not hesitate in taking robust enforcement action."
The retail company was found guilty of breaching section 2(1), relating to its own staff, and section 3(1), relating to members of the public and other workers, of the Health and Safety at Work etc Act 1974, on 18 July 2011. At the sentencing which took place at Bournemouth Crown Court on the 27 September 2011, the retail company was fined £1 million and ordered to pay costs of £600,000. These charges and fines relate to the Broad Street, Reading store and date from 24 April 2006 to 13 November 2006.
Contractor 1 was found guilty of contravening sections 2(1) and 3(1) of the Health and Safety at Work etc Act 1974 between 5 February 2007 and 28 February 2007, on 18 July 2011. At the sentencing which took place at Bournemouth Crown Court on 26 September 2011, they were fined £50,000 and ordered to pay costs of £75,000. These breaches took place at the store in Bournemouth.
Contractor 2 was found guilty, on the 18 July 2011,of contravening regulation 15 of the Control of Asbestos at Work Regulations 2002 between 5 May 2006 and 12 November 2006 at the store in Reading. At the sentencing which took place at Bournemouth Crown Court on 27 September 2011, they were fined £200. The company went into administration in December 2008 and now awaits dissolution.
At an earlier hearing on 12 January 2010, contractor 3 pleaded guilty to contravening sections 2(1) and 3(1) of the Health and Safety at Work etc Act 1974. These charges relate to offences committed between 24 April 2006 and 13 November 2006 at the store in Reading. At the sentencing which took place at Bournemouth Crown Court on 27 September 2011, they were fined £100,000 and ordered to pay costs of £40,000.



